Waving American Flag
Meredith Fire Department
9/11

On March 12, 2008, Town Meeting approved a $2.3 million bond for the addition to and renovation of the current Downtown Fire Station. Links for the sideshows tracking the progress of the project can be found at the bottom of the page or by clicking here.

A brief history follows:

Beginning in 1998 the need for expansion was identified and added to the CIP timeline.

In 2003 a Town-wide Space Needs Committee was appointed by the Select Board to analyze the facilities of Town Departments which, among others, identified the need for increased space for the Fire Department at approximately 7,000 square ft in addition to the current 6,600 square feet.

July 2005 saw the creation of an Internal Building Committee to begin the task of determining the current and future needs of the Fire Department. Among the major points in the charge to the committee was projecting ahead for twenty five years and beyond. Another was location. Could we stay where we were or was another location close to the current one an option?

The findings were as follows:

It was estimated that a building totaling 14,561 square feet would satisfy the current and future needs of the Department. It was also determined that the current site was the best location. Numerous factors were applied to determine the suitability of parcels that were identified through various means. As it turned out the Internal Committee recommended staying at the current site.

A Fire Station Building Advisory Committee was appointed by the Select Board in July 2006 and set to work. Their findings echoed the results of the Internal Committee. The Committee went before the Select Board in January 2007 to present their findings and to ask the Select Board to approve hiring an architect to move into the next phase of the project. Approval was obtained from the Select Board to contract with the firm of Sheerr McCrystal Palsen Architecture Inc. of New London for architectural services in late February 2007. Bauen Corporation was selected in March 2007 as the construction manager for the project. Final plans show a total of 15,243 square for the project, the larger number pertaining to hallways, stairs and such that the Internal Committee was unable to determine. Meeting minutes for the committee can be found here.

Site work commenced on April 15, 2008. Follow the links below to track the progress of the project!

Click on a thumbnail image for a larger view
Artistic Rendition
Building Elevations
Upper Level
Lower Level



Slide show links:


Copyright © 2001 - 2008     David E. Parker.     All Rights Reserved.